Alstom has signed a contract worth about $65 million with the Ministry of Electricity in Iraq for the rehabilitation of two units at Khor Al Zubair gas-fired power station, located in Basrah district, south of Iraq. Each unit is based on Alstom's GT13 gas turbine technology, originally commissioned in 1977. The first rehabilitated unit will be reconnected to the Iraqi electricity network in 2012 and the second unit will be connected before the summer peak of 2013.
Increase in output
The rehabilitation will increase the output of each unit by more than 30 MW, adding an extra 60 MWs to the electricity grid, when compared to their original rating. The project scope includes the upgrade of the units' compressors and gas turbines as well as replacement and upgrade of the electrical and control systems.
The upgrade will also increase the power plant efficiency and extend the life of the units. Equipment for the project will be produced at Alstom's factories in Europe and at Alstom's Jebel Ali service unit in Dubai. Alstom is also responsible for installation and commissioning of the unit.
This is Alstom's second rehabilitation project signed in recent times to rebuild Iraq's energy infrastructure. Alstom is currently also rehabilitating unit 1 of the Najaf gas-fired power station, south of Baghdad, which when completed will contribute again an output of 60 MW to the Iraqi electricity network. In December 2011, Alstom also signed a contract to build the 728 MW Al Mansuriya gas-fired power plant in the Diyala Governorate, northeast of Baghdad, expected to be in operation by early 2013.
First GE Vernova Aeroderivative Gas Turbine Operates on 100% Hydrogen
November 20th 2024The LM6000 gas turbine units feature a newly designed fuel nozzle, optimized water injection schedules, advanced control modifications, and safety features, including nitrogen purge systems and hydrogen fire detection systems.