Wood Group GTS has completed the installation of four EcoValue power augmentation systems on four GE Frame 7EA gas turbines at a 300MW cogeneration plant in Texas. The EcoValue system increases turbine output and efficiency and the plant is experiencing significant performance improvements, yielding 11.5% increase in power output and a 2.5% decrease in heat rate on one combined cycle block (two gas turbines and one steam turbine).
The EcoValue implementation followed an earlier performance improvement using similar technology. In 2009, the plant commissioned two compressor water wash systems that resulted in each turbine providing additional power output of up to 2 - 3 MW and a 0.2% - 0.3% improvement in heat rate.
Along with the supply of power to the plant's own air processing plant, excess power can now be sold into the local power distribution grid, while steam is provided to neighboring process facilities.
First GE Vernova Aeroderivative Gas Turbine Operates on 100% Hydrogen
November 20th 2024The LM6000 gas turbine units feature a newly designed fuel nozzle, optimized water injection schedules, advanced control modifications, and safety features, including nitrogen purge systems and hydrogen fire detection systems.