Siemens will build a combined cycle power plant as a turnkey project at the Marl Chemical Park in North Rhine-Westphalia, Germany. The order was placed by the specialty chemical group Evonik Industries. The new industrial power plant will consist of two units, each with an electrical capacity of 90 megawatts, and produce both electricity and process steam for the chemical park. The site’s integrated steam network will also supply district heat for about 2,000 homes in the future. The plant’s fuel efficiency will thus exceed 90 percent. With this combined cycle power plant, Evonik will replace its last coal-fired plant at the Marl Chemical Park. Because the plant will produce environmentally friendly electricity, process steam, and district heat from natural gas, the company will be able to cut CO2 emissions by one million metric tons per year.
Construction is scheduled to begin later in 2019, and the power plant is expected to go into operation in 2022. Siemens Financial Services (SFS), Siemens’ financing arm, developed a leasing financing solution specifically for Evonik in collaboration with Siemens Gas and Power. Together with the KfW IPEX Bank and LBBW, SFS will handle refinancing of the leasing agreement. The project volume is in the lower triple-digit million euro range.
“In building this power plant, whose technical and commercial concept was worked out jointly between Siemens and Evonik, we’re helping Evonik significantly cut its CO2 emissions,” said Michael Becker, CFO of Siemens Gas and Power. “In addition, the state-of-the-art plant will ensure a reliable supply of electricity and process steam for the chemical park. The ability to use various gases as fuel is another benefit and further increases the plant’s economic feasibility.”
Siemens’ scope of supply includes the turnkey construction of two identical power plant units as well as one industrial gas turbine, and one industrial steam turbine for each unit. It also includes generators, auxiliary systems, and the control system.
Siemens will carry out preventive maintenance work on both gas turbines for a period of 15 years under a long-term service agreement. This agreement also covers remote diagnostic services for daily plant monitoring and monthly analyses of the operating data. These digital services will ensure high plant availability.
Thanks to the use of special heat recovery steam generators and catalysts, the system can operate on natural gas as well as re-gasified liquefied natural gas (LNG), and various other gases, such as residual gas from production processes. Each power plant unit can produce not only electricity but also up to 220 metric tons of process steam per hour. Thanks to the plant’s high flexibility that enables it to compensate for the fluctuating infeed of renewable energy into the power grid and its ability to produce district heat, it is also supporting the energy transition in Germany.
Exhaust Gas Recirculation Boosts Carbon-Capture Efficiency and Reduces Costs, says GE Vernova
November 8th 2024Jeremee Wetherby, the Carbon Solutions Director at GE Vernova, offers deeper insights into the benefits of retrofitting carbon-capture systems with an exhaust gas recirculation system.
GE Vernova’s FEED Studies Reduce Carbon Capture Total, Operational Costs at Saudi Plants
November 5th 2024The studies targeted up to 32% by volume hydrogen blending with natural gas and identified modifications to the power generation assets, including exhaust gas recirculation to lower carbon-capture costs.